Construction Accounting Q&A Part 3 - Recognition and measurement.

01Confused over construction accounting Q&A Part III
Today we cover Q&A #3 on recognition and measurement in the construction accounting following our first sharing on the business cycle in last week.
We will run a series of our training note to our clients and new colleagues on contract accounting. Stay tune
Next is the tax treatment on the construction account.
02Step by step on construction accounting.
#1 Determine the % of completion
#1.1 Progress bill method
= Actual work done to date/contract sum
… OR
#1.2 Cost method
= Actual work done to date/budgeted cost
#2 Revenue Recognition = % of completion x contract sum
#3 Cost recognition = % of completion x budgeted cost
#4 Amount due / (to) from customer
#5 Disclosure on financial statement in construction accounting
#5.1 Recognition method used
#5.2 Amount due/(to) from customer
Visit us www.ktp.com.my
Visit us www.thks.com.my
— Visit Us
Come say hello.
Two firms in the heart of Taman Molek, Johor Bahru.

KTP & Company PLT
Wisma KTP, 53, 53-01 & 53-02, Jalan Molek 1/8, Taman Molek, 81100 Johor Bahru, Johor, Malaysia
THK Management Advisory
Wisma THK, No. 41, 41-01, 41-02, Jalan Molek 1/8, Taman Molek, 81100 Johor Bahru, Johor, Malaysia.— SOCIALS
Stay connected.
KTP
KTP Career
KTP Lifestyle
THK